Jawaharlal Nehru Technological University Hyderabad

Jawaharlal Nehru Technological University Hyderabad B.Tech IV MAINTENANCE AND SAFETY ENGINEERING Previous Question Paper (September - 2020 - R16)

B.Tech | IV | II | R16 | September - 2020

Answer PaperPaper Code: 138CZMaximum Marks: 75Time: 2 Hours

Answer any Five Questions. All Questions Carry Equal Marks.

Main

115 marks
a

Write notes on the engineering maintenance strategies for the 21st century.

7 marks

Answer

In the 21st century, maintenance has evolved from a reactive necessity to a proactive strategic function focused on reliability and asset lifecycle management. Key strategies include:

  • Reliability Centered Maintenance (RCM): A systematic approach to determine the maintenance requirements of physical assets based on their functional importance and failure modes.
  • Predictive Maintenance (PdM): Utilizing IoT sensors, big data analytics, and machine learning to monitor equipment condition in real-time, predicting failures before they occur to minimize downtime.
  • Total Productive Maintenance (TPM): A holistic approach involving all employees, from operators to management, to maximize equipment effectiveness through autonomous maintenance and continuous improvement.
  • Condition-Based Maintenance (CBM): Scheduling maintenance tasks only when specific indicators show decreasing performance or impending failure, optimizing resource allocation.
  • Digital Twin Technology: Creating virtual replicas of physical systems to simulate maintenance scenarios, test interventions, and optimize performance without risking actual operations.
b

You are given the following information about a project consisting of six activities. Construct the network diagram for this project and find the critical path.

ActivityImmediate PredecessorsEstimated Duration
A-5 months
B-1 month
CB2 months
DA, C4 months
EA6 months
FD, E3 months
8 marks

Answer

To construct the network diagram, we identify the sequence of activities:

  • Start node connects to A and B.
  • A leads to D and E.
  • B leads to C.
  • C leads to D.
  • D and E converge at F.

The paths and their durations are:

Path 1: A → D → F = 5 + 4 + 3 = 12 months
Path 2: A → E → F = 5 + 6 + 3 = 14 months
Path 3: B → C → D → F = 1 + 2 + 4 + 3 = 10 months

The critical path is the path with the longest duration, which is A → E → F, with a total duration of 14 months.

215 marks
a

Discuss the important elements of Effective Maintenance Management.

8 marks

Answer

Sign in to view the complete answer paper.

b

Distinguish between the PERT and CPM techniques.

7 marks

Answer

Sign in to view the complete answer paper.

315 marks
a

Derive the formulae for the E.O.Q., Optimal time between two consecutive production runs (or) two consecutive purchase orders, and the minimum total cost for the following Deterministic model: Economic Lot Size Model with Uniform Rate of Demand, Finite Rate of Replenishment, and having no Shortages.

8 marks

Answer

Sign in to view the complete answer paper.

b

Discuss the important elements of Preventive maintenance.

7 marks

Answer

Sign in to view the complete answer paper.

415 marks
a

Define Preventive maintenance. What is its primary goal?

7 marks

Answer

Sign in to view the complete answer paper.

b

Distinguish between Mean Preventive maintenance time, Maximum Preventive maintenance time, and Median Preventive maintenance time.

8 marks

Answer

Sign in to view the complete answer paper.

515 marks
a

Distinguish between the two types of maintenance budgeting approaches: Historical approach, Zero-based approach.

7 marks

Answer

Sign in to view the complete answer paper.

b

List at least ten maintenance safety-related questions for equipment manufacturers that can improve maintenance safety of their products.

8 marks

Answer

Sign in to view the complete answer paper.

615 marks
a

Give two examples of engineering system catastrophe due to poor-quality maintenance.

8 marks

Answer

Sign in to view the complete answer paper.

b

List the important reasons for the safety problems in maintenance.

7 marks

Answer

Sign in to view the complete answer paper.

715 marks
a

Define the following indices associated with RCM:

  • Emergency percentage index
  • Maintenance overtime percentage index
  • Equipment availability
7 marks

Answer

Sign in to view the complete answer paper.

b

What is the difference between hazard rate and failure rate? Explain with examples.

8 marks

Answer

Sign in to view the complete answer paper.

815 marks
a

Explain the following Maintainability Measures and Functions: Mean preventive maintenance time, Mean maintenance downtime.

8 marks

Answer

Sign in to view the complete answer paper.

b

Obtain maintainability functions for the following times to repair probability density functions:

  • Exponential
  • Lognormal
  • Gamma
7 marks

Answer

Sign in to view the complete answer paper.

About this paper

This page contains the solved question paper with answers of MAINTENANCE AND SAFETY ENGINEERING from Jawaharlal Nehru Technological University Hyderabad for B.Tech AME IV II, September - 2020, R16.

For the question paper without answers, switch to the Question Paper tab.

Other papers in MAINTENANCE AND SAFETY ENGINEERING

Loading Question Papers

Fetching data from database...