JNTU B.Tech II SURVEYING Previous Question Paper (August/September - 2022 - R16)

B.Tech | II | I | R16 | August/September - 2022

Answer PaperPaper Code: 133BUMaximum Marks: 75Time: 3 Hours

Answer any five questions. All questions carry equal marks.

Main

115 marks
a

Describe the different types of chains used in survey indicating the relative advantages of each.

8 marks

Answer

Surveying chains are classified based on their length and construction material. The primary types are:

  • Metric Chain: Available in 20m and 30m lengths, divided into 20cm links. These are the standard in modern surveying due to their decimal system, which simplifies calculations.
  • Gunter's Chain (Surveyor's Chain): 66 feet long with 100 links. It is specifically designed for land area measurements where 10 square chains equal 1 acre, making it highly advantageous for cadastral surveys.
  • Engineer's Chain: 100 feet long with 100 links. Each link is 1 foot long. It is preferred for large-scale engineering works where measurements are required in feet and inches.
  • Revenue Chain: 33 feet long with 16 links. It is primarily used for cadastral surveys in India for measuring small fields.
  • Steel Band (Band Chain): Consists of a long ribbon of steel with graduations. It is the most accurate type, though it is more fragile and prone to kinking compared to link chains.
b

Two stations A and B are not intervisible due to rising ground between them. Explain with a neat sketch, how the line AB can be ranged if both the stations are visible from intermediate points.

7 marks

Answer

When two stations A and B are not intervisible due to a hill, the process of indirect ranging (or reciprocal ranging) is employed. This requires two surveyors to stand at intermediate points M1 and N1 such that they can see both A and B.

The procedure is as follows:

  1. Two surveyors stand at M1 and N1, positioned such that M1 can see N1 and B, and N1 can see M1 and A.
  2. The surveyor at M1 directs the person at N1 to a new position N2 so that N2 is in line with M1 and B.
  3. The surveyor at N2 then directs the person at M1 to a new position M2 so that M2 is in line with N2 and A.
  4. This process of shifting the intermediate points is repeated until M and N are in a straight line with A and B.

The sketch involves a plan view showing the line AB obstructed by a central rise, with the points M1, N1 shifting iteratively to M, N until the line of sight is clear and collinear.

215 marks
a

Explain about basic principles of surveying.

7 marks

Answer

Sign in to view the complete answer paper.

b

A traverse ABCDA is made in the form of a square taking in clockwise order. If the bearing of AB is 120° 30′, find the bearing of the other sides.

8 marks

Answer

Sign in to view the complete answer paper.

315 marks
a

Find the height of a T-beam above the floor level. The R.L of the floor is 100.855 m and the staff reading on the floor is 2.055 m. The reading on a staff held upside down against the underside of the beam is 3.565 m.

8 marks

Answer

Sign in to view the complete answer paper.

b

Define a contour. State the various characteristics of contour lines.

7 marks

Answer

Sign in to view the complete answer paper.

4

The following perpendicular offsets were taken from a chain line.

Distance (m)051015203040506580
Offset (m)3.404.252.603.702.901.803.204.503.702.80

Calculate the area by: a) Trapezoidal rule and b) Simpson’s rule.

15 marks

Answer

Sign in to view the complete answer paper.

515 marks
a

List out the methods of measuring horizontal angles in theodolite surveying and also explain any one method in detail with a neat sketch.

7 marks

Answer

Sign in to view the complete answer paper.

b

An instrument was set up at A and the angle of elevation of the top of a tower BC was 26° 15′. The horizontal distance AB, B being the foot of the tower, was 715 m. Determine the R.L of the top of the tower, if the staff reading held on a station P of R.L. 100.0 m was 2.455 with the telescope horizontal.

8 marks

Answer

Sign in to view the complete answer paper.

6

The following data were collected while running a closed traverse ABCDA. Determine the missing data.

LineLength (m)Bearing
AB330181° 25′
BC?89° 50′
CD411355° 00′
DA827?
15 marks

Answer

Sign in to view the complete answer paper.

715 marks
a

What is meant by tacheometry? List the instruments needed for tacheometry.

6 marks

Answer

Sign in to view the complete answer paper.

b

Determine the values of stadia constants from the following observations.

Instrument stationDistance (m)Staff readings (Lower, Upper)
A1501.255, 2.750
B2001.000, 3.000
C2500.750, 3.255
9 marks

Answer

Sign in to view the complete answer paper.

815 marks
a

What are the objectives of a GPS?

6 marks

Answer

Sign in to view the complete answer paper.

b

What are three segments of GPS? Explain their functions briefly.

9 marks

Answer

Sign in to view the complete answer paper.

About this paper

This page contains the solved question paper with answers of SURVEYING from JNTU for B.Tech CE II I, August/September - 2022, R16.

For the question paper without answers, switch to the Question Paper tab.

Other papers in SURVEYING

Loading Question Papers

Fetching data from database...