JNTU

JNTU B.Tech III PRESTRESSED CONCRETE Previous Question Paper (August - 2022 - R18)

B.Tech | III | II | R18 | August - 2022

Answer PaperPaper Code: 156CNMaximum Marks: 75Time: 3 Hours

Answer any five questions. All questions carry equal marks.

Note: Use of only IS 1343 is allowed.

Main

1

Discuss in detail about pre-tensioning and Post tensioning and their advantages and limitations of Prestressed concrete.

15 marks

Answer

Pre-tensioning is a method of prestressing where the tendons are tensioned before the concrete is cast. The tendons are temporarily anchored against external abutments, concrete is poured around them, and once the concrete reaches the required strength, the tendons are released. The prestress is transferred to the concrete through bond along the length of the tendon.

Post-tensioning is a method where the tendons are tensioned after the concrete has hardened. Ducts are placed in the concrete formwork before casting. Once the concrete reaches sufficient strength, the tendons are inserted, stressed against the hardened concrete using hydraulic jacks, and anchored at the ends. The prestress is transferred through end-bearing.

Advantages of Pre-tensioning include suitability for mass production of standardized units, excellent bond characteristics, and elimination of end anchorages. Its limitations include the requirement for heavy casting beds and the inability to easily create curved cable profiles.

Advantages of Post-tensioning include its suitability for large-span cast-in-situ construction, the ability to use curved cable profiles to optimize stress distribution, and the reduction of dead load effects. Its limitations include the requirement for specialized anchorage devices, the need for grouting ducts to prevent corrosion, and higher labor costs due to complex site operations.

2

Explain about different methods of prestressing. Also explain about the necessity of high strength steel and concrete.

15 marks

Answer

Prestressing methods are broadly classified into two categories based on the sequence of tensioning the tendons relative to the casting of concrete:

  1. Pre-tensioning: In this method, tendons are tensioned before the concrete is cast. The tendons are anchored against strong abutments, concrete is poured, and once it gains sufficient strength, the tendons are released. The prestress is transferred to the concrete through bond between the steel and concrete.
  2. Post-tensioning: In this method, tendons are tensioned after the concrete has hardened. Concrete is cast with ducts for the tendons. Once the concrete reaches the required strength, the tendons are tensioned using hydraulic jacks and anchored against the hardened concrete member itself. The force is transferred through end-bearing plates.

The necessity for high-strength materials arises from the significant losses of prestress that occur over time. High-strength materials are essential for the following reasons:

  • High Strength Concrete: High-strength concrete is required to resist the high compressive stresses induced at the anchorage zones during prestressing and to minimize losses due to elastic shortening, creep, and shrinkage. It also provides superior bond strength for pre-tensioned members and better durability.
  • High Strength Steel: Prestressing steel must be of high strength to maintain a significant effective prestress force after accounting for losses such as relaxation of steel, creep, and shrinkage of concrete. If low-strength steel were used, the total initial prestress would be largely lost, rendering the prestressing ineffective. High-strength steel allows for the application of large tensioning forces while keeping the cross-sectional area of the tendons relatively small.
3

Discuss about Gifford- Udall and Magnel post tensioned systems.

15 marks

Answer

Sign in to view the complete answer paper.

415 marks
a

Explain Loss due to elastic shortening in post tensioned pre-stressed concrete.

4 marks

Answer

Sign in to view the complete answer paper.

b

A concrete beam is pre-stressed by a cable carrying an initial pre-stressing force of 800kN. The cross-sectional area of the wires in the cable is 400 mm2. Calculate the percentage loss of stress in the cable only due to shrinkage of concrete using IS: 1343 recommendations assuming the beam to be, (i) pre-tensioned and (ii) post-tensioned. Assume Es = 200 Gpa and age of concrete at transfer = 28 days.

11 marks

Answer

Sign in to view the complete answer paper.

5

The horizontal pre-stress at the centroid of a concrete beam of size 150mm × 300mm is 8Mpa and the maximum shear force on the beam is 80kN, calculate the maximum principal tensile stress. What is the minimum vertical pre-stress required eliminating this principal tensile stress?

15 marks

Answer

Sign in to view the complete answer paper.

6

A simply supported PSC beam of span 10m and cross section 500 mm × 750 mm. The beam is prestressed by a parabolic cable having eccentricity of 200 mm at the center and zero at the supports. The effective force in the cable is 1600 kN. If the beam supports a total UDL of 40 kN/m, including the self-weight, determine the extreme fiber stresses and force required in the cable having the same eccentricity to balance a total load of 50 kN/m on the beam.

15 marks

Answer

Sign in to view the complete answer paper.

7

The end block of a post tensioned concrete beam 450mm × 450mm is subjected to a concentric anchorage force of 800kN by a Freyssinet anchorage system of area 1200mm2. Discuss and detail the anchorage reinforcement for the end block.

15 marks

Answer

Sign in to view the complete answer paper.

8

The cross-sectional area of a concrete beam is 32×103 mm2 and the radius of gyration is 72mm is pre-stressed by a parabolic cable carrying an effective stress of 1200 N/mm. The span of the beam is 8m. The cable composed of 7 wires of 7mm diameter, has an eccentricity of 120mm at the centre and zero at the supports. Neglecting all losses, find the central deflection of the beam as follows:

15 marks
a

Self-weight + prestress

7 marks

Answer

Sign in to view the complete answer paper.

b

Self-weight + prestress + live load of 2 kN/m.

8 marks

Answer

Sign in to view the complete answer paper.

About this paper

This page contains the question paper of PRESTRESSED CONCRETE from JNTU for B.Tech CE III II, August - 2022, R18.

For the solved question paper with answers, switch to the Answer Paper tab.

Other papers in PRESTRESSED CONCRETE

Loading Question Papers

Fetching data from database...