a

What are the objectives and functions of construction management?

7 marks

Answer

The primary objective of construction management is to complete a project within the defined scope, budget, and time frame while maintaining high quality and safety standards. It aims to optimize resource utilization, minimize wastage, and ensure effective coordination among stakeholders.

The core functions include:

  • Planning: Defining project goals, schedules, and resource requirements.
  • Organizing: Establishing the project structure, assigning roles, and allocating resources.
  • Staffing: Selecting and deploying qualified personnel for specific tasks.
  • Directing: Providing leadership, motivation, and guidance to the project team.
  • Controlling: Monitoring progress against the plan, identifying deviations, and implementing corrective actions.
  • Coordinating: Ensuring seamless communication and integration between various departments and subcontractors.
b

Write a note on human resource management.

8 marks

Answer

Human Resource Management (HRM) in construction involves the strategic approach to managing the project workforce, from site laborers to project managers. Given the temporary and labor-intensive nature of construction, effective HRM is critical for project success.

Key aspects of HRM include:

  • Manpower Planning: Estimating the number and type of skilled/unskilled workers required at different stages of the project.
  • Recruitment and Selection: Sourcing personnel with the necessary technical skills and ensuring they meet safety and competency standards.
  • Training and Development: Providing regular safety training, skill enhancement programs, and tool-handling workshops to improve productivity and reduce accidents.
  • Performance Management: Evaluating worker output and quality of work to ensure targets are met.
  • Compensation and Welfare: Managing fair wages, incentives for timely completion, and ensuring basic health and safety welfare facilities on-site.
  • Conflict Resolution: Managing interpersonal issues and labor disputes to maintain a productive working environment.

Effective HRM ensures that the right people are available at the right time, fostering a culture of safety and efficiency that directly impacts the project's bottom line.

2

Discuss the importance of planning in construction management and brief on the type of organization structures suitable for different construction projects.

15 marks

Answer

Sign in to view the complete answer paper.

3

Explain briefly about planning for manpower, material and equipment.

15 marks

Answer

Sign in to view the complete answer paper.

415 marks
a

What are the factors to be considered in planning of manpower and materials?

7 marks

Answer

Sign in to view the complete answer paper.

b

Explain about resource analysis and resource allocation.

8 marks

Answer

Sign in to view the complete answer paper.

5

Explain Planning, Scheduling and controlling as a function of construction management?

15 marks

Answer

Sign in to view the complete answer paper.

6

Enlist the types of contract and explain any three types and brief on tender and tender documents for a construction project.

15 marks

Answer

Sign in to view the complete answer paper.

715 marks
a

Write about quality control and safety engineering in construction.

7 marks

Answer

Sign in to view the complete answer paper.

b

Describe some legal and financial aspects of accidents in construction.

8 marks

Answer

Sign in to view the complete answer paper.

8

Draw the CPM network diagram for the following data. Identify the critical path. Find the total duration of the project. Draw the tabular form showing EST, LST, EFT, LFT and FLOAT.

ActivityDuration
1-26
2-312
2-410
3-436
4-56
4-78
3-610
5-714
5-816
6-80
7-812
15 marks

Answer

Sign in to view the complete answer paper.

About this paper

This page contains the question paper of CONSTRUCTION MANAGEMENT from JAWAHARLAL NEHRU TECHNOLOGICAL UNIVERSITY HYDERABAD for B.Tech CEE IV Year I Semester, February/March - 2022, R16.

For the solved question paper with answers, switch to the Answer Paper tab.

Other papers in CONSTRUCTION MANAGEMENT

Loading Question Papers

Fetching data from database...