JAWAHARLAL NEHRU TECHNOLOGICAL UNIVERSITY HYDERABAD
JAWAHARLAL NEHRU TECHNOLOGICAL UNIVERSITY HYDERABAD B.Tech III Year POWER SYSTEM OPERATION AND CONTROL Previous Question Paper (August - 2022 - R18)
Answer any five questions. All questions carry equal marks.
Main
Explain the procedure for formation of nodal admittance matrix by step by step procedure.
Answer
The Nodal Admittance Matrix (Y-bus) is a fundamental tool in power system analysis, representing the relationship between nodal currents and voltages. The procedure to form this matrix is as follows:
- Step 1: Convert all given line impedances (Z) into admittances (Y) using the relation: Y = 1 / Z
- Step 2: Identify the number of buses (n) in the system. The Y-bus matrix will be an (n x n) square matrix.
- Step 3: Determine the Diagonal Elements (Yii): These are the sum of all admittances connected to bus 'i'. This includes the line admittances connected to other buses and any shunt admittances (like capacitors or reactors) connected directly to bus 'i'. Yii = Σ Yij (for all j connected to i) + Yshunt,i
- Step 4: Determine the Off-Diagonal Elements (Yij): These are the negative of the sum of all admittances directly connected between bus 'i' and bus 'j'. If no direct connection exists, Yij = 0. Yij = Yji = -yij
- Step 5: Assemble the matrix: Construct the matrix by placing the calculated diagonal and off-diagonal elements into the n x n structure.
Form the Y-bus for the network shown in figure, including the generator buses 1 and 2 with impedance of 0.1, 0.4 p.u. respectively. All the values are p.u. impedances for the network.
Answer
To form the Y-bus matrix for a system with generator impedances, we treat the generator internal impedance as a branch connected to a reference bus or as a shunt element if the generator is modeled as a voltage source behind an impedance.
Given the generator impedances (Zg1 = j0.1 p.u. and Zg2 = j0.4 p.u.), we first convert these to admittances:
Yg2 = 1 / j0.4 = -j2.5 p.u.
The diagonal elements of the Y-bus are modified by adding these generator admittances to the respective bus self-admittances:
- Y11 = (Sum of all admittances connected to bus 1) + Yg1
- Y22 = (Sum of all admittances connected to bus 2) + Yg2
The off-diagonal elements Yij remain the negative of the admittance of the line connecting bus i and bus j. If the network diagram shows a line with impedance Z12 between bus 1 and 2, then:
The final Y-bus matrix is then constructed as:
[ Y21 Y22 ]
Note: Ensure all units are in p.u. and complex arithmetic is performed correctly using the j operator.
Explain about the classification of buses with neat sketch.
Answer
Sign in to view the complete answer paper.
Explain Gauss-Seidel iterative method for power flow analysis of any power system with a flow chart.
Answer
Sign in to view the complete answer paper.
Derive generalized expression for transmission loss in a n-bus network.
Answer
Sign in to view the complete answer paper.
150 MW, 220 MW and 220 MW are the ratings of three units located in a thermal power station. Their respective incremental costs are given by the following equations. Determine the economical load allocation between the three units, when the total load on the station is (i) 350 MW (ii) 500 MW.
Answer
Sign in to view the complete answer paper.
Define penalty factor and state its significance.
Answer
Sign in to view the complete answer paper.
Derive relevant equations to explain economic dispatch of thermal plants coordinating the system transmission losses.
Answer
Sign in to view the complete answer paper.
Derive the model of speed governing system and hence draw its block diagram.
Answer
Sign in to view the complete answer paper.
A 100 MVA synchronous generator operates on full load at a frequency of 50 Hz. The load is suddenly reduced to 50 MW. Due to time lag in governor system, the steam valve begins to close after 0.4 sec. Determine the change in frequency that occurs in this time.
Answer
Sign in to view the complete answer paper.
What are the basic requirements needed for control strategy in Load Frequency Control (LFC) system.
Answer
Sign in to view the complete answer paper.
Obtain the mathematical modeling of tie line power in an inter connected system and its block diagram.
Answer
Sign in to view the complete answer paper.
Give the list of methods improving transient stability of the system.
Answer
Sign in to view the complete answer paper.
Derive the equal area criterion of stability and explain clearly how you can determine the stability limit of a synchronous motor when there is a sudden change in the mechanical load on the motor.
Answer
Sign in to view the complete answer paper.
What are the steps to be followed in planning of a computer control?
Answer
Sign in to view the complete answer paper.
Explain the implementation of SCADA system in the electric utility.
Answer
Sign in to view the complete answer paper.