JNTU B.Tech IV Year SOFTWARE PROJECT MANAGEMENT Previous Question Paper (November/December - 2018 - R15)

B.Tech | IV Year | I Semester | R15 | November/December - 2018

Answer PaperPaper Code: 127HPMaximum Marks: 75Time: 3 Hours

Note: This question paper contains two parts A and B. Part A is compulsory which carries 25 marks. Answer all questions in Part A. Part B consists of 5 Units. Answer any one full question from each unit.

Part A

125 marks
a

What is ROI? Discuss it in different domains.

2 marks

Answer

ROI stands for Return on Investment. It is a performance measure used to evaluate the efficiency of an investment or to compare the efficiency of a number of different investments.

The formula for ROI is:

ROI = (Net Profit / Cost of Investment) * 100

In different domains:

  • Finance: Used to compare the profitability of various investments, such as stocks, bonds, or real estate. A higher ROI indicates a more profitable investment.
  • Business/Marketing: Measures the effectiveness of marketing campaigns or business initiatives. For example, the ROI of an advertising campaign would be the profit generated by the campaign divided by its cost.
  • Software Project Management: Assesses the profitability of a software project. It helps in deciding whether to undertake a project by comparing the expected benefits (revenue, cost savings) against the project's development and maintenance costs.
b

What are the two basic steps in building a program? Explain them.

3 marks

Answer

The two basic steps in building a program are:

  1. Problem Solving: This involves understanding the problem that the program needs to solve, defining the requirements, and designing a solution. It's about figuring out *what* needs to be done and *how* it should be done logically. This includes breaking down the problem into smaller, manageable parts, identifying inputs and outputs, and outlining the steps the program will take.
  2. Implementation: This is the actual writing of the code based on the design created in the problem-solving phase. It involves translating the logical steps and algorithms into a specific programming language. This phase requires attention to syntax, data structures, and efficient coding practices to create a functional program.
c

What are the five characteristics of a successful object oriented project?

2 marks

Answer

Sign in to view the complete answer paper.

d

Explain the disadvantages of commercial components.

3 marks

Answer

Sign in to view the complete answer paper.

e

Explain a typical release specification outline.

2 marks

Answer

Sign in to view the complete answer paper.

f

What is meant by software architecture?

3 marks

Answer

Sign in to view the complete answer paper.

g

Discuss about life cycle architecture milestones.

2 marks

Answer

Sign in to view the complete answer paper.

h

Discuss about default distribution of effort and schedule by phase.

3 marks

Answer

Sign in to view the complete answer paper.

i

What is meant by process discriminants?

2 marks

Answer

Sign in to view the complete answer paper.

j

Write brief notes on process maturity.

3 marks

Answer

Sign in to view the complete answer paper.

Part B

2

Discuss about conventional software project management with its pros and cons.

10 marks

Answer

Sign in to view the complete answer paper.

OR
3

Explain about pragmatic software cost estimation model.

10 marks

Answer

Sign in to view the complete answer paper.

4

What are the various approaches for reducing software product size? Explain them.

10 marks

Answer

Sign in to view the complete answer paper.

OR
5

Discuss in detail about improving team effectiveness.

10 marks

Answer

Sign in to view the complete answer paper.

6

Explain a typical business case outline and a typical software development plan outline.

10 marks

Answer

Sign in to view the complete answer paper.

OR
7

Discuss about programmatic artifacts and engineering artifacts.

10 marks

Answer

Sign in to view the complete answer paper.

8

What is meant by workflows of the process? Discuss about iteration workflows?

10 marks

Answer

Sign in to view the complete answer paper.

OR
9

Discuss about minor milestones and periodic status assessments.

10 marks

Answer

Sign in to view the complete answer paper.

10

Explain about pragmatic software metrics.

10 marks

Answer

Sign in to view the complete answer paper.

OR
11

Discuss about the software project management principles with respect to CCPDS-R case study.

10 marks

Answer

Sign in to view the complete answer paper.

About this paper

This page contains the solved question paper with answers of SOFTWARE PROJECT MANAGEMENT from JNTU for B.Tech IT IV Year I Semester, November/December - 2018, R15.

For the question paper without answers, switch to the Question Paper tab.

Other papers in SOFTWARE PROJECT MANAGEMENT

Loading Question Papers

Fetching data from database...