a

List out various components in steam power plant.

2 marks

Answer

The main components of a steam power plant include the boiler, superheater, economizer, air preheater, steam turbine, condenser, cooling tower, feed water pump, and alternator.

b

What is the need of dust collectors in a steam power plant?

3 marks

Answer

Dust collectors are essential to remove fly ash and particulate matter from flue gases before they are discharged through the chimney. This is necessary to minimize air pollution, comply with environmental regulations, and prevent the accumulation of ash in the surrounding environment.

c

What are the functions of lubrication system?

2 marks

Answer

Sign in to view the complete answer paper.

d

What is the function of draught in gas turbine plant?

3 marks

Answer

Sign in to view the complete answer paper.

e

Write the list of advantages and disadvantages of water power.

2 marks

Answer

Sign in to view the complete answer paper.

f

What do you understand by hydrology? Explain the hydrological cycle.

3 marks

Answer

Sign in to view the complete answer paper.

g

What are the functions of a reflector?

2 marks

Answer

Sign in to view the complete answer paper.

h

What are homogeneous and heterogeneous reactors?

3 marks

Answer

Sign in to view the complete answer paper.

i

Write about diversity factor.

2 marks

Answer

Sign in to view the complete answer paper.

j

What is demand factor and its importance?

3 marks

Answer

Sign in to view the complete answer paper.

Part B

210 marks
a

Describe various methods used to fire pulverized coal.

5 marks

Answer

Sign in to view the complete answer paper.

b

How the energy resources are utilized in India for power generation and discuss the technological developments for power generation?

5 marks

Answer

Sign in to view the complete answer paper.

OR
310 marks
a

With the help of line diagram, explain the mechanical ash handling system.

5 marks

Answer

Sign in to view the complete answer paper.

b

Explain the working of over feed stoker with principle.

5 marks

Answer

Sign in to view the complete answer paper.

410 marks
a

Describe the working of a closed cycle gas turbine power plant. Mention its advantages and disadvantages.

5 marks

Answer

Sign in to view the complete answer paper.

b

Mention the different methods of fuel injection used in Diesel plants. Which method is mostly used?

5 marks

Answer

Sign in to view the complete answer paper.

OR
510 marks
a

Discuss the wet sump lubrication system pertaining to a diesel engine.

5 marks

Answer

Sign in to view the complete answer paper.

b

Draw the layout of combined cycle power generation unit and derive the equation for the thermal efficiency of the plant.

5 marks

Answer

Sign in to view the complete answer paper.

610 marks
a

What are typical ponds and storage units suitable for installation of hydroelectric power plants? Explain them.

5 marks

Answer

Sign in to view the complete answer paper.

b

What are the different factors to be considered while selecting the site for hydroelectric power plant?

5 marks

Answer

Sign in to view the complete answer paper.

OR
710 marks
a

Classify and explain the different types of dams and spill ways.

5 marks

Answer

Sign in to view the complete answer paper.

b

How are the Hydroelectric power plants classified? Explain them in detail.

5 marks

Answer

Sign in to view the complete answer paper.

810 marks
a

Draw the Nuclear reactor cross section and explain its working giving all details of components.

5 marks

Answer

Sign in to view the complete answer paper.

b

What are different breeding and fertile materials used for power generation in Nuclear reactors? Discuss them.

5 marks

Answer

Sign in to view the complete answer paper.

OR
910 marks
a

Enumerate the factors involved in selecting the materials for the various reactor components.

5 marks

Answer

Sign in to view the complete answer paper.

b

Explain in brief about radioactive waste disposal.

5 marks

Answer

Sign in to view the complete answer paper.

1010 marks
a

A generation station supplies the following loads 15MW, 12MW, 8MW and 0.5MW. The station has a maximum demand of 20MW and the annual load factor is 0.5. Find i) Number units supplied annually ii) Diversity factor.

5 marks

Answer

Sign in to view the complete answer paper.

b

Discuss briefly about the various methods available to restrict industrial pollution.

5 marks

Answer

Sign in to view the complete answer paper.

OR
1110 marks
a

The annual peak load on a 30 MW power station is 25MW. The power station supplies load having maximum demands of 10 MW, 8.5 MW, 5 MW, 4.5 MW. The annual load factor is 0.45. Calculate Average load, Diversity factor, Energy supplied per year and demand factor.

5 marks

Answer

Sign in to view the complete answer paper.

b

What are the effects of SO2, NO2 and hydrocarbons on the human and crop lives?

5 marks

Answer

Sign in to view the complete answer paper.

About this paper

This page contains the question paper of POWER PLANT ENGINEERING from JAWAHARLAL NEHRU TECHNOLOGICAL UNIVERSITY HYDERABAD for B.Tech ME IV I, January/February - 2023, R18.

For the solved question paper with answers, switch to the Answer Paper tab.