Briefly mention the importance of drilling operations in mining and construction.
Answer
Drilling is the primary operation in mining and construction used to create boreholes for placing explosives. It is essential for fragmenting rock mass efficiently, controlling the geometry of excavations, and ensuring safety and productivity in subsequent blasting operations.
List the various type of drilling equipments.
Answer
Drilling equipment is broadly categorized into:
- Percussive drills (Jackhammers, Drifters, Wagon drills)
- Rotary drills (Auger drills)
- Rotary-percussive drills (Down-the-hole drills, Top hammer drills)
- Jet piercing drills
Define Drillability of rock.
Answer
Sign in to view the complete answer paper.
State the mechanics of drilling.
Answer
Sign in to view the complete answer paper.
Define the term Detonators.
Answer
Sign in to view the complete answer paper.
Define the term Exploders.
Answer
Sign in to view the complete answer paper.
Define the term Ring blasting.
Answer
Sign in to view the complete answer paper.
List the statuary requirement of Blasting.
Answer
Sign in to view the complete answer paper.
List the environmental impact due to blasting.
Answer
Sign in to view the complete answer paper.
Explain the term Secondary Blasting.
Answer
Sign in to view the complete answer paper.
Part B
Describe the differences between the Double tube core barrels and wire line core barrels.
Answer
Sign in to view the complete answer paper.
List the limitation of Core recovery.
Answer
Sign in to view the complete answer paper.
Specify the importance of core logging in drilling operation.
Answer
Sign in to view the complete answer paper.
Explain the process of Directional drilling?
Answer
Sign in to view the complete answer paper.
Explain the Process of rotary drilling method with neat sketches and mention its applications.
Answer
Sign in to view the complete answer paper.
The density of rock is 2.4 g/cm and the diameter of the chips produced during the drilling 0.6 mm. Determine the bailing velocity (m/s) required to remove the chips from the hole?
Answer
Sign in to view the complete answer paper.
List the causes of Drill bit wear.
Answer
Sign in to view the complete answer paper.
Discuss the applicability and limitations for SMS and EMS.
Answer
Sign in to view the complete answer paper.
List the purpose of Relays.
Answer
Sign in to view the complete answer paper.
Discuss the composition of different detonator with sketch.
Answer
Sign in to view the complete answer paper.
Describe the term Safety Fuse.
Answer
Sign in to view the complete answer paper.
Explain the method and application of Drag Cut with neat sketch.
Answer
Sign in to view the complete answer paper.
List the precaution against mis-fire.
Answer
Sign in to view the complete answer paper.
List the precautions against the dangers due to blasting below ground.
Answer
Sign in to view the complete answer paper.
Explain the method and application of Wedge cut.
Answer
Sign in to view the complete answer paper.
Explain in detail about Controlled blasting.
Answer
Sign in to view the complete answer paper.
Describe any one method in detail with neat sketches.
Answer
Sign in to view the complete answer paper.
Describe the Dimensional stone blasting.
Answer
Sign in to view the complete answer paper.
List the Preventive measures for fly rocks.
Answer
Sign in to view the complete answer paper.