JNTU B.Tech IV ROCK SLOPE TECHNOLOGY Previous Question Paper (March 2021 - R16)

B.Tech | IV | I | R16 | March 2021

Answer PaperPaper Code: 137GW/127HGMaximum Marks: 75Time: 3 Hours

Answer any Five Questions. All Questions Carry Equal Marks.

Main

115 marks
a

State various geometrical parameters depend on the overall slope angle for Slope design.

7 marks

Answer

The overall slope angle is a critical design parameter that dictates the stability and efficiency of a rock slope. The primary geometrical parameters dependent on the overall slope angle include:

  1. Bench Height: The vertical distance between the crest and the toe of a bench, which must be optimized relative to the overall slope angle to ensure structural integrity.
  2. Bench Face Angle: The inclination of the individual bench face, which is typically steeper than the overall slope angle.
  3. Catch Bench Width: The horizontal width of the bench surface designed to catch falling debris; as the overall slope angle decreases, the required catch bench width often increases to maintain safety.
  4. Inter-ramp Angle: The angle formed by the slope of the rock mass between two major haulage ramps, which is constrained by the overall slope design.
  5. Slope Height: The total vertical distance from the crest of the uppermost bench to the toe of the lowest bench, which directly influences the required overall slope angle for stability.
b

How overall pit slope and mine economics are connected?

8 marks

Answer

The relationship between the overall pit slope and mine economics is defined by the trade-off between safety and the volume of waste rock removal. A steeper overall pit slope significantly improves the economics of a mining project through the following mechanisms:

  1. Stripping Ratio Reduction: A steeper slope reduces the amount of overburden or waste rock that must be excavated to access the ore body. This directly lowers the stripping ratio, leading to substantial savings in drilling, blasting, and haulage costs.
  2. Increased Ore Recovery: By steepening the walls, more ore that would otherwise be locked under a shallow slope can be recovered, thereby increasing the total mineable reserves and the net present value (NPV) of the project.
  3. Capital Expenditure: Steeper slopes allow for a smaller surface footprint, which can reduce the costs associated with land acquisition, environmental mitigation, and infrastructure development.
  4. Risk and Stability Costs: Conversely, there is an economic limit; if the slope is made too steep, the probability of slope failure increases. The cost of potential failures—including equipment loss, production delays, and remediation expenses—must be weighed against the gains from reduced waste removal.

In summary, the optimal overall slope angle is the one that maximizes the project's profit by balancing the cost of waste removal against the geotechnical risk of failure.

215 marks
a

Draw the diagram of a pit slope undergoing circular failure and mention the equilibrium equation and define the parameters used.

7 marks

Answer

Sign in to view the complete answer paper.

b

Calculate the factor of safety against shear failure along the slip circle (BEC) passing through toe and crest of the slope as shown in Figure. Assume cohesion 40 kN/m3. The height of the slope is 50 m and overall slope angle of line BC is 26° with the horizontal. H=50 m, R=115.8 m x = 65.28 m

8 marks

Answer

Sign in to view the complete answer paper.

315 marks
a

Discuss the water management plane to increase the factor of safety of a slope in water bearing strata?

7 marks

Answer

Sign in to view the complete answer paper.

b

Enumerate the factors affecting the stability of rock slopes in opencast mines.

8 marks

Answer

Sign in to view the complete answer paper.

415 marks
a

Explain detail Investigations of failed slopes in Opencast mines benches.

7 marks

Answer

Sign in to view the complete answer paper.

b

List the Slope Monitoring Instruments.

8 marks

Answer

Sign in to view the complete answer paper.

515 marks
a

Describe the kinematics of topping failure of rock slopes and its types.

8 marks

Answer

Sign in to view the complete answer paper.

b

Explain the prevention and remedial of landslides.

7 marks

Answer

Sign in to view the complete answer paper.

615 marks
a

Distinguish between the estimation of factor of safety of dry and wet slope undergoing a planar failure.

7 marks

Answer

Sign in to view the complete answer paper.

b

Explain Circular failure analysis for the stability with FLAC –Software.

8 marks

Answer

Sign in to view the complete answer paper.

7

Briefly explain the Bishop’s method of failure analysis of a circular failure.

15 marks

Answer

Sign in to view the complete answer paper.

815 marks
a

Distinguish between factor of safety of a dry slope and a wet slope undergoing planar failure.

7 marks

Answer

Sign in to view the complete answer paper.

b

Name the different types of slope failures that may take place in Opencast mines and give the conditions necessary to exist for one type failure to take place.

8 marks

Answer

Sign in to view the complete answer paper.

About this paper

This page contains the solved question paper with answers of ROCK SLOPE TECHNOLOGY from JNTU for B.Tech MNE-MIE IV I, March 2021, R16.

For the question paper without answers, switch to the Question Paper tab.