What are the applications of OR? Discuss how and why OR methods have been valuable in aiding executive decisions.
Answer
Operations Research (OR) finds applications in finance (portfolio management), production (scheduling and inventory control), marketing (media selection), logistics (transportation and routing), and healthcare (resource allocation). OR methods are valuable to executives because they provide a quantitative basis for decision-making, replacing intuition with analytical models. By simulating complex scenarios and identifying optimal solutions, OR helps executives minimize costs, maximize efficiency, and mitigate risks under conditions of uncertainty.
What are the assumptions of job sequencing?
Answer
The standard assumptions for job sequencing problems include:
- Each job is processed through machines in a specific, predetermined order.
- Only one job can be processed on a machine at any given time.
- Processing times are known and constant.
- Setup times are negligible or included in the processing time.
- Jobs are independent of each other.
- Machines are continuously available for work.
Give the essential characteristics of the queuing process? State some of the important inter-arrival and service time distributions?
Answer
Sign in to view the complete answer paper.
What is an inventory system? Explain clearly the different costs that are involved in inventory problems with suitable examples.
Answer
Sign in to view the complete answer paper.
Explain Maxi-Min principle used in game theory?
Answer
Sign in to view the complete answer paper.
Part B
Solve following problems using Big – M method. Minimize 60X1 + 80X2. Constraints: 20X1+30X2 ≥ 900; 40X1+30X2 ≥ 1200; X1, X2 ≥ 0.
Answer
Sign in to view the complete answer paper.
A company has three production facilities S1, S2 and S3 with production capacity of 7, 9 and 18 units (in 100s) per week of a product, respectively. These units are to be shipped to four warehouses D1, D2, D3 and D4 with requirement of 5, 6, 7 and 14 units (in 100s) per week, respectively. Formulate this transportation problem as an LP model to minimize the total transportation cost.
Answer
Sign in to view the complete answer paper.
There are five jobs, each of which must go through the two machines A and B in the order AB. Processing times are given below for Jobs 1, 2, 3, 4, 5. Time for A: 5, 1, 9, 3, 10; Time for B: 2, 6, 7, 8, 4. Determine a sequence for five jobs that will minimize the elapsed time T.
Answer
Sign in to view the complete answer paper.
A milk plant is considering replacement of a machine whose cost price is Rs. 12,200 and the scrap value Rs. 200. The running (maintenance and operating) costs in Rs. for years 1 through 8 are: 200, 500, 800, 1200, 1800, 2500, 3200, 4000. When should the machine be replaced?
Answer
Sign in to view the complete answer paper.
In a railway marshaling yard, goods trains arrive at a rate of 30 trains per day. Assuming that the inter arrival time follows an exponential distribution and the service time distribution is also exponential with an average of 36 minutes. Calculate: a) The average no. of trains in the queue, b) The probability that the queue size exceeds 10. If the input of trains increases to an average 33 per day, what will be change in (a) and (b).
Answer
Sign in to view the complete answer paper.
A mechanic services 4 machines. For each machine, the mean time between service requirements is 10 hours and is assumed to be from an exponential distributions. The repair time tends to follow the same distribution with a mean of two hours. When a machine is down for repairs the time lost has a value of Rs.20 per hour. The mechanic costs Rs.50 per day. Find: a) What are the expected no. of machines in operation? b) What is the expected down time cost per day? c) Would it be desirable to provide two mechanics each to service only two machines?
Answer
Sign in to view the complete answer paper.
The annual demand of an item is 3200 units. The unit cost is Rs.6/- and inventory carrying charges 25% per annum. If the cost of one procurement is Rs.150/-, determine: a) Economic order quantity, b) No. of orders per year, c) Time between two consecutive orders, d) The optimal cost.
Answer
Sign in to view the complete answer paper.
Consider the following data: Unit cost = Rs.100, Order cost = Rs.160, Inventory carrying cost = Rs.20, Back order cost (Stock out cost) = Rs.10, Annual demand = 1000 units. Compute the following: a) Minimum cost order quantity, b) Time between orders, c) Minimum number of back orders, d) Maximum inventory level, e) Overall annual cost.
Answer
Sign in to view the complete answer paper.
Find the saddle point (or points) and hence solve the game for Player A (A1, A2, A3) and Player B (B1, B2, B3) with values: A1(15, 2, 3), A2(6, 5, 7), A3(-7, 4, 0).
Answer
Sign in to view the complete answer paper.
What is Dynamic programming and what sort of problems can be solved by it? State and establish Bellman’s principle of optimality.
Answer