1

Prepare the approximate cost of building project (group Housing) with the following details:

a) No. of houses = 150

b) Plinth area of each dwelling = 600m2

c) Plinth area rate = Rs. 5,000/- per m2

d) Cost of water supply & sanitary arrangements @ 12½%

e) Electrification at 7½% of cost of building

f) Cost of roads & Lawns @ 5%

g) Cost of P.S. & contingencies @ 4%

15 marks

Answer

To calculate the approximate cost of the group housing project, we first determine the total plinth area and the base building cost, followed by the addition of various percentage-based provisions.

  1. Total Plinth Area: 150 houses × 600 m2/house = 90,000 m2
  2. Base Building Cost: 90,000 m2 × Rs. 5,000/m2 = Rs. 45,00,00,000
  3. Additions:
    • Water supply & sanitary (12.5%): 0.125 × 45,00,00,000 = Rs. 5,62,50,000
    • Electrification (7.5%): 0.075 × 45,00,00,000 = Rs. 3,37,50,000
    • Roads & Lawns (5%): 0.05 × 45,00,00,000 = Rs. 2,25,00,000
  4. Sub-total: 45,00,00,000 + 5,62,50,000 + 3,37,50,000 + 2,25,00,000 = Rs. 56,25,00,000
  5. Contingencies & P.S. (4% of sub-total): 0.04 × 56,25,00,000 = Rs. 2,25,00,000
  6. Total Estimated Cost: 56,25,00,000 + 2,25,00,000 = Rs. 58,50,00,000

The total approximate cost of the project is Rs. 58,50,00,000 (Fifty-eight crores and fifty lakhs only).

2

Prepare the detailed estimate for the following items of work for the building:

a) R.C.C. (1:1.5:3) in columns upto ground level only.

b) R.C.C. (1:2:4) in plinth beams.

15 marks

Answer

To prepare a detailed estimate for R.C.C. works, we calculate the volume by multiplying the length, breadth, and height/depth of each structural member. The estimate is prepared in a standard measurement sheet format.

Item No.Description of WorkNo.Length (m)Breadth (m)Height/Depth (m)Quantity (m³)
1R.C.C. (1:1.5:3) in columns upto GLnLBHn × L × B × H
2R.C.C. (1:2:4) in plinth beamsnLBHn × L × B × H

Steps for calculation:

  • Identify the number of columns and their respective cross-sectional dimensions from the structural drawings.
  • Measure the height of the columns from the top of the footing to the ground level (GL).
  • For plinth beams, calculate the total center-to-center length of the beams and adjust for overlaps at junctions to avoid double counting.
  • Multiply the number of units by the dimensions to obtain the total volume in cubic meters.
  • Deduct the volume of steel reinforcement (usually 1% to 2% of total volume) if specified by the project requirements, though typically, standard estimates for R.C.C. include the volume of concrete required for the member size.
  • Summarize the quantities in an abstract sheet, applying current schedule of rates (SSR) to arrive at the total cost.
3

Calculate the volume of earth work for part of a road from the following data:

Chainage in mts600630660690720750780810840870900
RL in mts61.2061.2560.9061.2560.8060.4560.2060.3559.1059.4559.7

FL in mts starts at 60.00 with an upward gradient of 1 in 200.

15 marks

Answer

Sign in to view the complete answer paper.

4

A RCC beam of 8m length, 0.35m breadth and 0.45m depth is reinforced with 2 No. of diameter 12mm @ top, 4 No. of diameter 20mm @ bottom, stirrups 2L diameter 8mm @ 175mm c/c is provided throughout its length. Estimate the cost of RCC beam.

15 marks

Answer

Sign in to view the complete answer paper.

5

Calculate the quantity of materials for the following items:

15 marks
a
C.M. (1:4) for 1m3 of work
7 marks

Answer

Sign in to view the complete answer paper.

b
C.M. (1:6) for 1m3 of work
8 marks

Answer

Sign in to view the complete answer paper.

6

Calculate the quantity of Cement required in bags for the following items of work:

15 marks
a
C.C. (1:4:8) using 40mm HBG metals for 30m3 of work
7 marks

Answer

Sign in to view the complete answer paper.

b
RR masonry in CM (1:5) using 0.34m3 of CM for 1m3 of masonry for 20m3 of work
8 marks

Answer

Sign in to view the complete answer paper.

7

Explain the following terms:

a) Administrative Approval

b) Technical sanction

c) Budget provision

d) Expenditure sanction

15 marks

Answer

Sign in to view the complete answer paper.

8

An equipment that was purchased at a cost of Rs 20 lakhs, six years ago is considered for replacement. The existing equipment can be sold at a price of Rs. 5 lakhs and if kept for another six years will have salvage value of Rs. 1 lakh. The challenger has annual operating cost of Rs. 50,000/- and its salvage value is Rs. 5 lakhs at the end of 12 years. Rate of interest is 10%. Decide whether to continue services of existing equipment or replace it.

15 marks

Answer

Sign in to view the complete answer paper.

About this paper

This page contains the question paper of ESTIMATION, COSTING AND PROJECT MANAGEMENT from JAWAHARLAL NEHRU TECHNOLOGICAL UNIVERSITY HYDERABAD for B.Tech CE IV IV-I, February/March - 2022, R18.

For the solved question paper with answers, switch to the Answer Paper tab.

Other papers in ESTIMATION, COSTING AND PROJECT MANAGEMENT

Loading Question Papers

Fetching data from database...