JNTU

JNTU B.Tech III PRODUCTION PLANNING AND CONTROL Previous Question Paper (August/September - 2021 - R18)

B.Tech | III | III-II | R18 | August/September - 2021

Answer PaperPaper Code: 156CQMaximum Marks: 75Time: 3 Hours

Answer any five questions. All questions carry equal marks.

Main

115 marks
a

Distinguish between Production planning and Production control with suitable examples.

7 marks

Answer

Production planning is the pre-production activity focused on determining what, how, when, and where to produce. It involves setting objectives, forecasting demand, and scheduling resources to ensure optimal utilization. For example, a furniture manufacturer planning the production of 500 chairs by scheduling raw material procurement and allocating labor hours for the next month is engaged in production planning.

Production control is the execution phase that monitors and regulates the production process to ensure it adheres to the plan. It involves dispatching, progress reporting, and taking corrective actions if deviations occur. For example, if the furniture manufacturer discovers a machine breakdown or a shortage of wood, production control intervenes to reschedule tasks or adjust the workflow to meet the original deadline.

b

Discuss the major factors contributing to the complexity of production control.

8 marks

Answer

The complexity of production control arises from several dynamic factors that disrupt planned operations:

  • Demand Variability: Fluctuations in customer orders and market trends make it difficult to maintain stable production schedules, often leading to either stockouts or excess inventory.
  • Process Complexity: In multi-stage manufacturing, the interdependency of various operations means that a delay in one department (e.g., machining) creates a bottleneck that propagates through the entire system.
  • Resource Unreliability: Unplanned equipment downtime, maintenance requirements, and labor absenteeism directly impact the capacity and throughput of the production line.
  • Supply Chain Disruptions: Delays in the arrival of raw materials or components from suppliers can halt production, requiring constant adjustments to the production sequence.
  • Product Variety: High-mix, low-volume production environments require frequent setup changes and retooling, which increases the complexity of scheduling and sequencing tasks.
  • Quality Issues: The occurrence of defective parts necessitates rework or scrap, which consumes additional resources and disrupts the planned flow of production.
215 marks
a

What is meant by ‘Decomposition of a Time Series’? Explain with examples.

7 marks

Answer

Sign in to view the complete answer paper.

b

Here are the quarterly data for the past two years. From these data, prepare a forecast for the upcoming year using decomposition.

PeriodActual
1300
2540
3885
4580
5416
6760
71191
8760
8 marks

Answer

Sign in to view the complete answer paper.

315 marks
a

What is an inventory system and what purpose does it serve? Explain.

6 marks

Answer

Sign in to view the complete answer paper.

b

Given the following information, formulate an inventory management system. The item is demanded 50 weeks a year. Item Cost Rs. 10.00, Order cost Rs. 250.00, Annual holding Cost 33% of item cost, Annual demand 25,750 (515 per week), Standard deviation of weekly demand 25 per week, Lead time 1 week, Service probability 95%.

  1. State the order quantity and reorder point.
  2. Determine the annual holding and order costs.
  3. If a price break of Rs. 50 per order was offered for purchase of quantities of over 2,000, would you take advantage of it? How much would you save annually?
9 marks

Answer

Sign in to view the complete answer paper.

415 marks
a

Define mixed strategy. Why would a firm use a mixed strategy instead of a simple pure strategy?

8 marks

Answer

Sign in to view the complete answer paper.

b

What are the major limitations of using the transportation method for aggregate planning?

7 marks

Answer

Sign in to view the complete answer paper.

5

The following tasks must be performed on an assembly line in the sequence and times specified:

TaskTask Time (Sec)Preceding Tasks
A50-
B40-
C20A
D45C
E20C
F25D
G10E
H35B,F,G
15 marks
a

Draw the schematic diagram.

5 marks

Answer

Sign in to view the complete answer paper.

b

What is the theoretical minimum number of stations required to meet a forecast demand of 400 units per eight-hour day?

5 marks

Answer

Sign in to view the complete answer paper.

c

Use the longest-task-time rule and balance the line in the minimum number of stations to produce 400 units per day.

5 marks

Answer

Sign in to view the complete answer paper.

615 marks
a

What are factors affecting the routing procedure? Explain their significance.

8 marks

Answer

Sign in to view the complete answer paper.

b

What is Alternative routing? When is it considered? Discuss in detail.

7 marks

Answer

Sign in to view the complete answer paper.

715 marks
a

Distinguish between single machine scheduling and flow shop scheduling.

7 marks

Answer

Sign in to view the complete answer paper.

b

Consider the following 2 machines and 6 jobs flow shop problem. Obtain the optimal schedule and the corresponding make span.

JobMachine 1Machine 2
157
2108
3813
497
5611
61210
8 marks

Answer

Sign in to view the complete answer paper.

815 marks
a

Discuss briefly the role of expediting and the procedures followed for expediting in production control.

7 marks

Answer

Sign in to view the complete answer paper.

b

Discuss, in detail, any two computer application areas of production planning and control.

8 marks

Answer

Sign in to view the complete answer paper.

About this paper

This page contains the question paper of PRODUCTION PLANNING AND CONTROL from JNTU for B.Tech ME III III-II, August/September - 2021, R18.

For the solved question paper with answers, switch to the Answer Paper tab.

Other papers in PRODUCTION PLANNING AND CONTROL

Loading Question Papers

Fetching data from database...