JNTU B.Tech III PRODUCTION PLANNING AND CONTROL Previous Question Paper (February - 2023 - R18)

B.Tech | III | III-II | R18 | February - 2023

Answer PaperPaper Code: 156CQMaximum Marks: 75Time: 3 Hours

Note: i) Question paper consists of Part A, Part B. ii) Part A is compulsory, which carries 25 marks. In Part A, Answer all questions. iii) In Part B, Answer any one question from each unit. Each question carries 10 marks and may have a, b as sub questions.

Part A

125 marks
a

The table below indicates the monthly demand for the six months period for a product.

Month123456
Demand (Units)125130105145115130

Determine the sales forecast for the 7th month, using a 3 month simple moving average method.

2 marks

Answer

The 3-month simple moving average for the 7th month is calculated by taking the average of the demands for months 4, 5, and 6:

Forecast = (Demand4 + Demand5 + Demand6) / 3

Forecast = (145 + 115 + 130) / 3 = 390 / 3 = 130 units.

b

How can one evaluate the Production Planning and Control (PPC) function?

3 marks

Answer

PPC function evaluation is performed by measuring performance against set objectives using key performance indicators (KPIs) such as:

  • Schedule Adherence: Comparing actual production output against the planned production schedule.
  • Inventory Turnover: Assessing how efficiently inventory is being utilized to meet demand.
  • Resource Utilization: Analyzing the capacity utilization of machines and labor to identify bottlenecks or idle time.
c

Distinguish between Independent and Dependent demand in inventory management.

2 marks

Answer

Sign in to view the complete answer paper.

d

Distinguish between in-process inventory, safety stock inventory and seasonal inventory.

3 marks

Answer

Sign in to view the complete answer paper.

e

Distinguish between pure and mixed strategies in production planning.

2 marks

Answer

Sign in to view the complete answer paper.

f

Explain briefly the Just-in-time inventory system (JIT).

3 marks

Answer

Sign in to view the complete answer paper.

g

What is Line of Balance (LOB)?

2 marks

Answer

Sign in to view the complete answer paper.

h

Distinguish between finite and infinite loading and forward and backward scheduling.

3 marks

Answer

Sign in to view the complete answer paper.

i

Explain the main activities of a dispatcher.

2 marks

Answer

Sign in to view the complete answer paper.

j

Comment upon the significance of material follow-up role of the purchase department.

3 marks

Answer

Sign in to view the complete answer paper.

Part B

2

Explain diagrammatically the production/operations management cycle and explain the levels of production planning in detail.

10 marks
a

Explain diagrammatically the production/operations management cycle.

5 marks

Answer

Sign in to view the complete answer paper.

b

Explain the levels of production planning in detail.

5 marks

Answer

Sign in to view the complete answer paper.

OR
310 marks
a

Discuss the steps in the Delphi method of forecasting.

4 marks

Answer

Sign in to view the complete answer paper.

b

XYZ company used simple exponential method using an exponential smoothing constant of 0.25 to forecast the short term demand. The forecast for the month of January was 1,000 units whereas the actual sales were only 900 units. What is the forecast for the month of August?

6 marks

Answer

Sign in to view the complete answer paper.

410 marks
a

Briefly explain VED analysis.

4 marks

Answer

Sign in to view the complete answer paper.

b

Magnum Enterprises requires 90,000 units of a certain item annually. It costs Rs.3 per unit. The cost per purchase order is Rs.300 and the inventory carrying cost is Rs.20 percent per year. i) What is the EOQ if there is no discount? ii) What should the firm do if the supplier offers discounts as below?

Order quantityDiscount(%)
4,500-5,9992
6,000 and above3
6 marks

Answer

Sign in to view the complete answer paper.

OR
5

Pranit Engineering Contractors (PEC) creates six-month “rolling” schedules which are recomputed monthly. For competitive reasons PEC does not subcontract. Therefore, its only options to meet customer requirements are (a) work on regular time; (b) work on over time, which is limited to 30 percent of regular time; (c) do customers’ work early, which would cost an additional Rs. 50 per hour per month.; and (d) perform customers’ work late, which would cost an additional Rs. 100 per month penalty, as provided by their contract. PEC has 25 engineers on its staff at an hourly rate of Rs.300. The overtime rate is Rs.450. Customers’ hourly requirements for the six months from January to June are: January: 5,000; February: 4,000; March: 6,000; April: 6,000; May: 5,000; June: 4,000. Develop an aggregate plan using a spreadsheet. Assume 20 working days in each month.

10 marks

Answer

Sign in to view the complete answer paper.

6

The following tasks must be performed on an assembly line in the sequence and times specified. a) Draw the schematic diagram. b) What is the theoretical minimum number of stations required to meet a forecast demand of 400 units per eight-hour day? c) Use the longest-task-time and balance the line in the minimum number of stations to produce 400 units per day.

TaskTask time (Seconds)Immediate predecessor
A50-
B40-
C20A
D45C
E20C
F25D
G10E
H35B,F,G
10 marks

Answer

Sign in to view the complete answer paper.

OR
710 marks
a

Explain the use of route sheet as a common production management tool.

5 marks

Answer

Sign in to view the complete answer paper.

b

How is an operation and route sheet different from a process flow chart? Explain taking a suitable example.

5 marks

Answer

Sign in to view the complete answer paper.

810 marks
a

What do you understand by scheduling? Discuss the different approaches to scheduling.

5 marks

Answer

Sign in to view the complete answer paper.

b

There are six jobs which must go through two machines A and B in the order AB. Obtain the optimal sequence of the jobs and the elapsed time.

Jobs123456
Machine A81011121620
Machine B7501439
5 marks

Answer

Sign in to view the complete answer paper.

OR
910 marks
a

Distinguish between Loading and Dispatching.

5 marks

Answer

Sign in to view the complete answer paper.

b

Explain the following single criterion sequencing rules in detail: i) FCFS ii) SPT iii) EDD iv) LPT

5 marks

Answer

Sign in to view the complete answer paper.

10

Discuss in detail the dispatching procedures and various forms used in dispatching.

10 marks

Answer

Sign in to view the complete answer paper.

OR
1110 marks
a

How does the expediting function play a crucial role in keeping the job moving through the production facility on time?

5 marks

Answer

Sign in to view the complete answer paper.

b

Discuss the applications of computers in planning and control.

5 marks

Answer

Sign in to view the complete answer paper.

About this paper

This page contains the question paper of PRODUCTION PLANNING AND CONTROL from JNTU for B.Tech ME III III-II, February - 2023, R18.

For the solved question paper with answers, switch to the Answer Paper tab.