JAWAHARLAL NEHRU TECHNOLOGICAL UNIVERSITY HYDERABAD

JAWAHARLAL NEHRU TECHNOLOGICAL UNIVERSITY HYDERABAD B.Tech IV PRODUCTION PLANNING AND CONTROL Previous Question Paper (December - 2020 - R16)

B.Tech | IV | IV-II | R16 | December - 2020

Answer PaperPaper Code: 138EGMaximum Marks: 75Time: 2 Hours

Answer any Five Questions

All Questions Carry Equal Marks

Main

1

Write about characteristics of various types of production systems.

15 marks

Answer

Production systems are categorized based on the nature of the product, volume of production, and variety of product mix. The three primary types are Job Shop, Batch, and Mass/Continuous production.

1. Job Shop Production
This system involves the production of small quantities of products designed and produced as per customer specifications. Characteristics include:

  • High variety of products with low volume.
  • Use of general-purpose machines and equipment.
  • Highly skilled operators capable of handling varied tasks.
  • Large inventory of raw materials and work-in-progress.
  • Complex production planning and scheduling due to frequent changes.

2. Batch Production
In this system, products are produced in batches or lots. It is a middle ground between job shop and mass production. Characteristics include:

  • Moderate variety and moderate volume of production.
  • Equipment is used for a specific batch and then reset for the next.
  • Standardized sequence of operations for each batch.
  • Lower unit cost compared to job shop production.
  • Requires efficient material handling and inventory control to manage batch transitions.

3. Mass Production
This involves the continuous production of standardized products in large quantities. Characteristics include:

  • Very high volume with very low product variety.
  • Use of special-purpose machines and automated production lines.
  • Flow-line layout where work moves sequentially from one station to the next.
  • Low skill requirement for operators as tasks are repetitive.
  • High initial capital investment but very low unit production cost.
  • Balanced production lines to minimize idle time.

4. Continuous Production
An extreme form of mass production where the product is produced in a continuous flow, often used in process industries like oil refineries or chemical plants. Characteristics include:

  • 24/7 operation with no interruptions.
  • Highly automated and integrated systems.
  • Material flows through the process without human intervention.
  • Very high capital intensity and low labor cost.
  • Strict quality control and maintenance protocols to prevent system downtime.
2

A electrical Contractor’s record during the last five weeks indicate the number of job requests:

Week12345
Requests2022182122

Predict the number of requests for week 6 using each of the following methods:

15 marks
a

Naïve

5 marks

Answer

The Naïve method assumes that the forecast for the next period is equal to the actual value of the most recent period. Given that the actual requests for week 5 were 22, the forecast for week 6 is 22.

b

A three year moving average method

5 marks

Answer

Sign in to view the complete answer paper.

c

Exponential smoothing with α=0.30. Use 20 for week 2 forecast.

5 marks

Answer

Sign in to view the complete answer paper.

3

Suppose a company produces a type of desk that has the BOM given below. The desk is made by assembling two drawers, two handles, one drawer frame, and two legs into a drawer module. Then two drawer modules, desk back and a desk top are assembled into a desk.

Level NoItem descriptionNo.RequiredLead Time(Weeks)
00Desk1
01Desk top12
01Desk back11
01Leg/drawer module21
02Drawer frame11
02Desk legs21
02Drawers22
02Handles22

For the following desk requirements, construct:

15 marks
a

the material requirement plans for the desk

7 marks

Answer

Sign in to view the complete answer paper.

b

Desk top and Desk back.

8 marks

Answer

Sign in to view the complete answer paper.

4

Twelve tasks, with times and precedence requirements as shown in the following table, are to be assigned to workstations using a cycle time of 1.5 minutes.

TaskLength (minutes)Immediate Predecessor
a0.1-
b0.2a
c0.9b
d0.6c
e0.1-
f0.2d,e
g0.4f
h0.1g
i0.2h
j0.7i
k0.3j
l0.2k
15 marks
a

Draw the precedence diagram for this line.

7 marks

Answer

Sign in to view the complete answer paper.

b

Compute the % of idle time and efficiency according to RPW method.

8 marks

Answer

Sign in to view the complete answer paper.

5

The processing times for 7 jobs on three machines A, B, and C are shown in the Table below, and the processing order for all the jobs on the three machines is A-C-B. Determine the optimal sequence of the jobs for processing on the three machines, and also find the total elapsed time.

Job No.1234567
Processing Time on A (Hrs)3874987
Processing Time on B (Hrs)675115612
Processing Time on C (Hrs)4325143
15 marks

Answer

Sign in to view the complete answer paper.

6

List out various charts used in LOB and explain about each with a diagram.

15 marks

Answer

Sign in to view the complete answer paper.

7

State and explain various steps involved in dispatching procedure.

15 marks

Answer

Sign in to view the complete answer paper.

8

State and explain various applications of computer in production planning and controlling functions.

15 marks

Answer

Sign in to view the complete answer paper.

About this paper

This page contains the solved question paper with answers of PRODUCTION PLANNING AND CONTROL from JAWAHARLAL NEHRU TECHNOLOGICAL UNIVERSITY HYDERABAD for B.Tech ME IV IV-II, December - 2020, R16.

For the question paper without answers, switch to the Question Paper tab.

Other papers in PRODUCTION PLANNING AND CONTROL