JAWAHARLAL NEHRU TECHNOLOGICAL UNIVERSITY HYDERABAD
JAWAHARLAL NEHRU TECHNOLOGICAL UNIVERSITY HYDERABAD B.Tech IV PRODUCTION PLANNING AND CONTROL Previous Question Paper (December - 2020 - R16)
Answer any Five Questions
All Questions Carry Equal Marks
Main
Write about characteristics of various types of production systems.
Answer
Production systems are categorized based on the nature of the product, volume of production, and variety of product mix. The three primary types are Job Shop, Batch, and Mass/Continuous production.
1. Job Shop Production
This system involves the production of small quantities of products designed and produced as per customer specifications. Characteristics include:
- High variety of products with low volume.
- Use of general-purpose machines and equipment.
- Highly skilled operators capable of handling varied tasks.
- Large inventory of raw materials and work-in-progress.
- Complex production planning and scheduling due to frequent changes.
2. Batch Production
In this system, products are produced in batches or lots. It is a middle ground between job shop and mass production. Characteristics include:
- Moderate variety and moderate volume of production.
- Equipment is used for a specific batch and then reset for the next.
- Standardized sequence of operations for each batch.
- Lower unit cost compared to job shop production.
- Requires efficient material handling and inventory control to manage batch transitions.
3. Mass Production
This involves the continuous production of standardized products in large quantities. Characteristics include:
- Very high volume with very low product variety.
- Use of special-purpose machines and automated production lines.
- Flow-line layout where work moves sequentially from one station to the next.
- Low skill requirement for operators as tasks are repetitive.
- High initial capital investment but very low unit production cost.
- Balanced production lines to minimize idle time.
4. Continuous Production
An extreme form of mass production where the product is produced in a continuous flow, often used in process industries like oil refineries or chemical plants. Characteristics include:
- 24/7 operation with no interruptions.
- Highly automated and integrated systems.
- Material flows through the process without human intervention.
- Very high capital intensity and low labor cost.
- Strict quality control and maintenance protocols to prevent system downtime.
A electrical Contractor’s record during the last five weeks indicate the number of job requests:
| Week | 1 | 2 | 3 | 4 | 5 |
| Requests | 20 | 22 | 18 | 21 | 22 |
Predict the number of requests for week 6 using each of the following methods:
Naïve
Answer
The Naïve method assumes that the forecast for the next period is equal to the actual value of the most recent period. Given that the actual requests for week 5 were 22, the forecast for week 6 is 22.
A three year moving average method
Answer
Sign in to view the complete answer paper.
Exponential smoothing with α=0.30. Use 20 for week 2 forecast.
Answer
Sign in to view the complete answer paper.
Suppose a company produces a type of desk that has the BOM given below. The desk is made by assembling two drawers, two handles, one drawer frame, and two legs into a drawer module. Then two drawer modules, desk back and a desk top are assembled into a desk.
| Level No | Item description | No.Required | Lead Time(Weeks) |
|---|---|---|---|
| 00 | Desk | 1 | |
| 01 | Desk top | 1 | 2 |
| 01 | Desk back | 1 | 1 |
| 01 | Leg/drawer module | 2 | 1 |
| 02 | Drawer frame | 1 | 1 |
| 02 | Desk legs | 2 | 1 |
| 02 | Drawers | 2 | 2 |
| 02 | Handles | 2 | 2 |
For the following desk requirements, construct:
the material requirement plans for the desk
Answer
Sign in to view the complete answer paper.
Desk top and Desk back.
Answer
Sign in to view the complete answer paper.
Twelve tasks, with times and precedence requirements as shown in the following table, are to be assigned to workstations using a cycle time of 1.5 minutes.
| Task | Length (minutes) | Immediate Predecessor |
|---|---|---|
| a | 0.1 | - |
| b | 0.2 | a |
| c | 0.9 | b |
| d | 0.6 | c |
| e | 0.1 | - |
| f | 0.2 | d,e |
| g | 0.4 | f |
| h | 0.1 | g |
| i | 0.2 | h |
| j | 0.7 | i |
| k | 0.3 | j |
| l | 0.2 | k |
Draw the precedence diagram for this line.
Answer
Sign in to view the complete answer paper.
Compute the % of idle time and efficiency according to RPW method.
Answer
Sign in to view the complete answer paper.
The processing times for 7 jobs on three machines A, B, and C are shown in the Table below, and the processing order for all the jobs on the three machines is A-C-B. Determine the optimal sequence of the jobs for processing on the three machines, and also find the total elapsed time.
| Job No. | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
|---|---|---|---|---|---|---|---|
| Processing Time on A (Hrs) | 3 | 8 | 7 | 4 | 9 | 8 | 7 |
| Processing Time on B (Hrs) | 6 | 7 | 5 | 11 | 5 | 6 | 12 |
| Processing Time on C (Hrs) | 4 | 3 | 2 | 5 | 1 | 4 | 3 |
Answer
Sign in to view the complete answer paper.
List out various charts used in LOB and explain about each with a diagram.
Answer
Sign in to view the complete answer paper.
State and explain various steps involved in dispatching procedure.
Answer
Sign in to view the complete answer paper.
State and explain various applications of computer in production planning and controlling functions.
Answer
Sign in to view the complete answer paper.