JNTU B.Tech IV ADVANCED SURFACE MINING Previous Question Paper (July/August - 2022 - R18)
Answer any five questions. All questions carry equal marks.
Main
What is cutoff grade of ore and its estimation? Explain.
Answer
The cutoff grade is the minimum concentration of a valuable mineral in an ore body that allows for its extraction and processing at a profit. It serves as the threshold distinguishing between ore (profitable material) and waste (non-profitable material).
Estimation involves evaluating the total costs of mining, processing, and marketing against the market value of the recovered metal. The fundamental formula is:
Key factors influencing estimation include:
- Operating Costs: Includes drilling, blasting, loading, hauling, and milling expenses.
- Metal Price: Fluctuations in global commodity markets directly impact the profitability threshold.
- Metallurgical Recovery: The efficiency of the extraction process in capturing the metal from the ore.
- Economic Parameters: Royalties, taxes, and overheads that must be deducted from the revenue.
Explain the DPR-contents and its preparation in detail.
Answer
A Detailed Project Report (DPR) is a comprehensive document that outlines the technical, financial, and environmental feasibility of a mining project. It serves as the blueprint for investment decisions and operational planning.
Key contents of a DPR include:
- Geological Report: Details on ore reserves, grade distribution, and rock mechanics.
- Mining Plan: Selection of mining method, equipment fleet size, production scheduling, and bench design.
- Infrastructure Requirements: Layout for haul roads, power supply, water management, and waste rock dumps.
- Financial Analysis: Capital expenditure (CAPEX), operating expenditure (OPEX), internal rate of return (IRR), and net present value (NPV) calculations.
- Environmental and Social Impact: Mitigation strategies for dust, noise, water pollution, and rehabilitation plans.
Preparation involves multidisciplinary collaboration between geologists, mining engineers, financial analysts, and environmental consultants. It begins with site investigation and data collection, followed by feasibility studies, design optimization, and finally, formal approval from regulatory authorities.
What is ultimate pit configuration and its determination? Explain.
Answer
Sign in to view the complete answer paper.
Explain the hand method, floating cone technique of open pit optimization in detail.
Answer
Sign in to view the complete answer paper.
Explain the influence of pit slope on mine economics in detail.
Answer
Sign in to view the complete answer paper.
Explain in detail the stability analysis and design methodology for waste dumps.
Answer
Sign in to view the complete answer paper.
Explain the following:
Stockpiling and blending
Answer
Sign in to view the complete answer paper.
Spreaders and Reclaimers
Answer
Sign in to view the complete answer paper.
Computerized truck dispatch.
Answer
Sign in to view the complete answer paper.
Explain the power supply arrangements in opencast mines.
Answer
Sign in to view the complete answer paper.
Discuss the maintenance scheduling, preventive maintenance in opencast mines.
Answer
Sign in to view the complete answer paper.
Explain the occupational health hazards due to the following:
Mine dust.
Answer
Sign in to view the complete answer paper.
Poor lighting and ventilation
Answer
Sign in to view the complete answer paper.
Noise and vibration
Answer
Sign in to view the complete answer paper.
Radioactive emission.
Answer
Sign in to view the complete answer paper.
Explain the in pit crushing and conveying.
Answer
Sign in to view the complete answer paper.
Discuss the Placer mining and solution mining and its scope of applicability.
Answer
Sign in to view the complete answer paper.