JAWAHARLAL NEHRU TECHNOLOGICAL UNIVERSITY HYDERABAD

JAWAHARLAL NEHRU TECHNOLOGICAL UNIVERSITY HYDERABAD B.Tech IV PLANNING OF UNDERGROUND COAL MINING PROJECT Previous Question Paper (September - 2020 - R15)

B.Tech | IV | II | R15 | September - 2020

Answer PaperPaper Code: 128DPMaximum Marks: 75Time: 2 hours

Answer any Five Questions. All Questions Carry Equal Marks.

Main

115 marks
a

Differentiate between a Mining Industry and other related industries.

7 marks

Answer

The mining industry is fundamentally distinct from other manufacturing or processing industries due to the nature of its resource base, operational constraints, and economic risks. The primary differences are as follows:

  • Depleting Asset Base: Unlike manufacturing industries that source raw materials from external suppliers, the mining industry consumes its own capital asset (the mineral deposit). Once extracted, the resource is non-renewable and cannot be replaced, leading to the eventual closure of the operation.
  • Geological Uncertainty: Mining projects operate under significant geological risk. While manufacturing processes are generally predictable and repeatable, mining involves extracting a commodity from a variable, heterogeneous, and often hidden underground environment, making resource estimation and grade control inherently uncertain.
  • Location Specificity: Manufacturing plants can often be relocated to optimize logistics or labor costs. Mining operations are strictly tied to the geographical location of the mineral deposit, often requiring development in remote or difficult terrains.
  • High Capital Intensity and Long Lead Times: Mining projects require massive upfront capital investment for exploration, mine development, and infrastructure before any revenue is generated. The time from initial discovery to production is typically much longer than in other industrial sectors.
  • Environmental and Social Impact: Mining has a unique and profound impact on the surface and subsurface environment, requiring complex reclamation and closure planning that is not typically required to the same extent in other industries.
b

What are the principles of planning?

8 marks

Answer

Planning in the context of underground coal mining is a systematic process designed to optimize resource extraction while ensuring safety, economic viability, and regulatory compliance. The core principles include:

  • Principle of Objective Setting: Every plan must have clearly defined, measurable goals, such as daily production targets, safety benchmarks, or specific recovery percentages. These objectives guide the selection of mining methods and equipment.
  • Principle of Efficiency and Economy: The plan must aim to minimize the cost per ton of coal produced. This involves selecting the most suitable mining technology (e.g., longwall vs. bord and pillar) and optimizing the logistics of transport, ventilation, and power supply.
  • Principle of Safety and Conservation: Safety is the paramount principle. Planning must incorporate robust strata control, effective ventilation, and fire protection measures. Furthermore, the principle of conservation ensures maximum extraction of the coal seam while minimizing waste and preventing subsidence damage to the surface.
  • Principle of Flexibility: Because mining conditions can change unexpectedly due to geological disturbances (faults, folds, or gas outbursts), a plan must be adaptable. It should allow for modifications to the mining sequence or layout without compromising the overall project integrity.
  • Principle of Integration: A mine plan is not an isolated document; it must integrate various subsystems including production, electrical, mechanical, civil, and safety departments to ensure a cohesive operational workflow.
  • Principle of Sustainability: Modern planning must account for the life-cycle of the mine, including environmental mitigation, waste management, and a comprehensive mine closure plan that addresses post-mining land use.
2

Explain what are the factors that will be kept in mind while planning an underground coal mine producing 1 million tonne of coal production?

15 marks

Answer

Sign in to view the complete answer paper.

3

What are the geological factors to be considered while preparing a mine plan? How they are going to be influenced while preparing a mine plan?

15 marks

Answer

Sign in to view the complete answer paper.

4

What are different methods of extraction of coal? What are different characteristics that influence the Long wall method of mining? Explain.

15 marks

Answer

Sign in to view the complete answer paper.

5

A coal seam of 'C' grade coal having 3.2 m in height and dipping at 1 in 7 and has normal water seepage has to be extracted? Which method do you suggest for extraction of coal? Explain its advantages and disadvantages.

15 marks

Answer

Sign in to view the complete answer paper.

6

Differentiate the economics of Advanced Long wall method of extraction with retreating method of extraction? If the safety, production and productivity are the basic criterias, Which method is more suitable. Explain?

15 marks

Answer

Sign in to view the complete answer paper.

7

What are different types of Supports used in Gate Roads and Mechanized Long wall Faces?

15 marks

Answer

Sign in to view the complete answer paper.

8

What is angle of Draw? Explain the features which influence the angle of draw? Explain them in brief.

15 marks

Answer

Sign in to view the complete answer paper.

About this paper

This page contains the question paper of PLANNING OF UNDERGROUND COAL MINING PROJECT from JAWAHARLAL NEHRU TECHNOLOGICAL UNIVERSITY HYDERABAD for B.Tech MNE-MIE IV II, September - 2020, R15.

For the solved question paper with answers, switch to the Answer Paper tab.

Other papers in PLANNING OF UNDERGROUND COAL MINING PROJECT

Loading Question Papers

Fetching data from database...