JNTU B.Tech IV Year MINE PLANNING Previous Question Paper (March - 2021 - R16)

B.Tech | IV Year | I Semester | R16 | March - 2021

Answer PaperPaper Code: 137EQMaximum Marks: 75Time: 3 Hours

Answer any Five Questions. All Questions Carry Equal Marks.

Main

115 marks
a

What are the technical factors to be considered in mine planning?

7 marks

Answer

Technical factors in mine planning are critical for ensuring safety, economic viability, and operational efficiency. The primary technical factors include:

  • Geological characteristics: Detailed assessment of ore body geometry, thickness, dip, depth, and structural discontinuities, along with the physical and chemical properties of the ore and host rock.
  • Geotechnical parameters: Rock mass rating (RMR), stress conditions, and stability analysis to determine appropriate support systems and slope angles for open pits or pillar dimensions for underground mines.
  • Mine method selection: Choosing between open-pit or underground methods based on depth, stripping ratio, and ore body continuity.
  • Production capacity and scheduling: Determining the optimal extraction rate based on equipment performance, lead times, and market demand.
  • Infrastructure and logistics: Planning for haulage systems, ventilation requirements, power supply, drainage, and waste rock disposal sites.
  • Mineral processing and recovery: Evaluating the metallurgical characteristics to ensure efficient beneficiation and high recovery rates.
b

What is a long term approach in mine planning and design?

8 marks

Answer

A long-term approach in mine planning involves strategic decision-making that spans the entire life-of-mine (LOM), typically covering periods of 10 to 30 years or more. This approach focuses on maximizing the net present value (NPV) of the project while ensuring sustainable resource extraction.

Key components of the long-term approach include:

  1. Strategic Reserve Estimation: Defining the total mineable reserves and establishing cut-off grades that remain economically viable over the long term despite market fluctuations.
  2. Ultimate Pit or Mine Limit Design: Determining the final boundaries of the mine to ensure the most efficient extraction of the ore body while minimizing the stripping ratio.
  3. Capital Expenditure (CAPEX) Planning: Phasing major investments in heavy machinery, processing plants, and site infrastructure to align with production milestones.
  4. Environmental and Closure Planning: Incorporating progressive reclamation, tailings management, and final mine closure strategies from the early design stages to mitigate long-term environmental liabilities.
  5. Flexibility and Risk Management: Building in contingencies for geological uncertainty, commodity price volatility, and regulatory changes to ensure the mine remains resilient throughout its operational life.
215 marks
a

Write short notes on EMP (Environment Management Plan)?

7 marks

Answer

Sign in to view the complete answer paper.

b

What are the techniques of mine modeling?

8 marks

Answer

Sign in to view the complete answer paper.

315 marks
a

Explain about Corporate social responsibility.

7 marks

Answer

Sign in to view the complete answer paper.

b

Give the salient features of pre-feasibility report of an Opencast coal mine.

8 marks

Answer

Sign in to view the complete answer paper.

415 marks
a

What are different factors to be considered for successful operation of inpit crushing?

7 marks

Answer

Sign in to view the complete answer paper.

b

With a neat block diagram, give concept of mine scheduling of an open pit. Give the basic principles involved in proper scheduling to achieve good productivity and higher net present values.

8 marks

Answer

Sign in to view the complete answer paper.

515 marks
a

Explain in detail the methodology of mine planning you would adopt for large opencast metal mine. Assume your own conditions wherever necessary.

7 marks

Answer

Sign in to view the complete answer paper.

b

What factors influence the locations of box-cut in opencast mines?

8 marks

Answer

Sign in to view the complete answer paper.

615 marks
a

Draw layout of Three(3) Heading Panel for Bord and Pillar and indicate ventilation network.

7 marks

Answer

Sign in to view the complete answer paper.

b

Explain the various aspects to be considered for ventilation planning for large underground coal mine.

8 marks

Answer

Sign in to view the complete answer paper.

715 marks
a

What are the factors that influence size of panel in coal mines?

7 marks

Answer

Sign in to view the complete answer paper.

b

Explain the scope of automation / mechanization in Underground Coal mines.

8 marks

Answer

Sign in to view the complete answer paper.

815 marks
a

What are the technical factors to be considered in selection of drilling machines?

7 marks

Answer

Sign in to view the complete answer paper.

b

How do you monitor the performance of a dumper?

8 marks

Answer

Sign in to view the complete answer paper.

About this paper

This page contains the question paper of MINE PLANNING from JNTU for B.Tech MNE-MIE IV Year I Semester, March - 2021, R16.

For the solved question paper with answers, switch to the Answer Paper tab.