JNTU B.Tech IV Year MINE PLANNING Previous Question Paper (September - 2021 - R16)

B.Tech | IV Year | I Semester | R16 | September - 2021

Answer PaperPaper Code: 137EQMaximum Marks: 75Time: 3 hours

Answer any Five Questions

All Questions Carry Equal Marks

Main

115 marks
a

What is Mine Modelling? Discuss its importance in planning.

7 marks

Answer

Mine modelling is the process of creating a digital, three-dimensional representation of a mineral deposit, including its geological structure, grade distribution, and rock mass characteristics. It integrates data from drill holes, geophysical surveys, and geological mapping into a coherent spatial database.

Its importance in planning includes:

  • Resource Estimation: Provides accurate calculations of ore tonnage and grade, which are fundamental for economic feasibility studies.
  • Risk Mitigation: Allows for the identification of geological uncertainties and structural hazards before mining commences.
  • Optimization: Enables the simulation of different mining sequences and pit designs to maximize the net present value (NPV) of the project.
  • Operational Efficiency: Facilitates precise scheduling, equipment selection, and waste management strategies.
b

Describe the methodology of Mine planning.

8 marks

Answer

The methodology of mine planning is a structured, iterative process designed to convert a mineral resource into a profitable mining operation. The key steps are:

  1. Data Collection and Validation: Gathering geological, geotechnical, and metallurgical data to build a reliable block model.
  2. Economic Parameters Definition: Establishing cut-off grades, commodity prices, operating costs, and capital expenditure requirements.
  3. Pit Optimization: Utilizing algorithms (such as the Lerchs-Grossmann or Pseudoflow) to determine the ultimate economic pit limit based on the block model and economic constraints.
  4. Mine Design: Designing the physical layout, including haul roads, benches, ramps, and waste rock dumps, ensuring compliance with safety and environmental regulations.
  5. Production Scheduling: Sequencing the extraction of ore and waste over the life of the mine to meet production targets and processing capacity.
  6. Financial Analysis: Evaluating the project's viability through cash flow modeling, sensitivity analysis, and NPV calculation.
  7. Review and Iteration: Continuously updating the plan based on actual operational performance and changing market conditions.
2

Explain about the geological factors, which control the Mine Design and explain the monitoring mechanism.

15 marks

Answer

Sign in to view the complete answer paper.

315 marks
a

What are the purposes of mine closure plan? Discuss in detail.

5 marks

Answer

Sign in to view the complete answer paper.

b

How do you develop a calendar plan for large Opencast mine considering the following parameters such as production, overburden, stripping ratio and output per man shift?

10 marks

Answer

Sign in to view the complete answer paper.

415 marks
a

What are the parameters to be monitored during slope stability monitoring? Explain.

8 marks

Answer

Sign in to view the complete answer paper.

b

Discuss about the factors which influence the stability of slopes.

7 marks

Answer

Sign in to view the complete answer paper.

515 marks
a

Explain the typical factors used in determining mine size?

7 marks

Answer

Sign in to view the complete answer paper.

b

Four benches are being worked by the opencast mining system. Height, width and face angle for each bench are 20m, 30 m and 75° respectively. Find out the overall slope angle of the benches in Degrees?

8 marks

Answer

Sign in to view the complete answer paper.

615 marks
a

Explain the conditions suitable for deployment of Continuous Miner Technology.

8 marks

Answer

Sign in to view the complete answer paper.

b

What are the benefits of Continuous Miner Technology?

7 marks

Answer

Sign in to view the complete answer paper.

7

Explain the methodology adopted for planning a large underground mechanized coal mines and discuss in detail.

15 marks

Answer

Sign in to view the complete answer paper.

815 marks
a

What are the latest technological developments in both, types and capacities of equipment used in mining operations?

8 marks

Answer

Sign in to view the complete answer paper.

b

Describe the methodology of selection of equipment for different mining conditions?

7 marks

Answer

Sign in to view the complete answer paper.

About this paper

This page contains the question paper of MINE PLANNING from JNTU for B.Tech MNE-MIE IV Year I Semester, September - 2021, R16.

For the solved question paper with answers, switch to the Answer Paper tab.

Other papers in MINE PLANNING

Loading Question Papers

Fetching data from database...