Answer PaperPaper Code: 844AGMaximum Marks: 75Time: 3hrs

Note: This question paper contains two parts A and B. Part A is compulsory which carries 25 marks. Answer all questions in Part A. Part B consists of 5 Units. Answer any one full question from each unit. Each question carries 10 marks and may have a, b, c as sub questions.

Part A

125 marks
a

What are the salient features of team software process? Compare with personal software process.

5 marks

Answer

The Team Software Process (TSP) is designed to build self-directed teams that plan, track, and manage their own work. Its salient features include team-based planning, defined roles for team members, rigorous quality management through inspections, and the use of quantitative data to manage project performance. While the Personal Software Process (PSP) focuses on improving the performance of an individual developer by tracking their own time and defects, TSP extends these principles to the team level, emphasizing team commitment, collective ownership, and coordinated effort to achieve project goals.

b

Differentiate between meta process and macro process.

5 marks

Answer

A meta process is a process for creating, managing, or improving other processes; it defines how a software development process itself is structured, evaluated, and evolved. In contrast, a macro process refers to the high-level, end-to-end lifecycle of a software project, encompassing the major phases from requirements gathering and design to implementation, testing, and deployment. Essentially, the macro process describes the 'what' and 'when' of project execution, while the meta process describes the 'how' of process engineering.

c

What is achieved by visible milestones in the life cycle?

5 marks

Answer

Sign in to view the complete answer paper.

d

List the responsibilities of software architecture team over the project life cycle.

5 marks

Answer

Sign in to view the complete answer paper.

e

Depict the real results of major mile stones in a modern process.

5 marks

Answer

Sign in to view the complete answer paper.

Part B

2

Describe the six step process for improving the software process.

10 marks

Answer

Sign in to view the complete answer paper.

OR
3

What are the characteristics of CMM level3 organization? Discuss the key actions required to advance to level 4 organizations.

10 marks

Answer

Sign in to view the complete answer paper.

4

Describe five improvements to the basic waterfall process that would eliminate most of the development risks.

10 marks

Answer

Sign in to view the complete answer paper.

OR
510 marks
a

How are implementation sets are evaluated, assessed and measured?

5 marks

Answer

Sign in to view the complete answer paper.

b

Elaborate primary evaluation criteria of inception phase.

5 marks

Answer

Sign in to view the complete answer paper.

6

What is meant by a workflow? What are the seven top-level workflows? Explain the relative levels of effort expected across the phases in these workflows.

10 marks

Answer

Sign in to view the complete answer paper.

OR
710 marks
a

Compare top-down and bottom-up approaches of project planning.

5 marks

Answer

Sign in to view the complete answer paper.

b

What is the basic content of status assessment reviews?

5 marks

Answer

Sign in to view the complete answer paper.

8

The project organization represents the architecture of the team and needs to evolve consistent with the project plan captured in the work break down structure. Explain how the team’s centre of gravity shifts over the life cycle.

10 marks

Answer

Sign in to view the complete answer paper.

OR
910 marks
a

Discuss change traffic as a quality indicator.

5 marks

Answer

Sign in to view the complete answer paper.

b

What are the goals of software metrics?

5 marks

Answer

Sign in to view the complete answer paper.

10

How does a modern process framework exploit several critical approaches to resolve recurring issues in the conventional projects? Give illustrative example.

10 marks

Answer

Sign in to view the complete answer paper.

OR
11

Demonstrate any five best practices for software project management.

10 marks

Answer

Sign in to view the complete answer paper.

About this paper

This page contains the question paper of SOFTWARE PROCESS AND PROJECT MANAGEMENT from JNTU for MCA 2019 IV, April/May - 2019, R17.

For the solved question paper with answers, switch to the Answer Paper tab.

Other papers in SOFTWARE PROCESS AND PROJECT MANAGEMENT

Loading Question Papers

Fetching data from database...