JNTU B.Tech II POWER SYSTEMS I Previous Question Paper (December - 2018 - R13)
Note: This question paper contains two parts A and B. Part A is compulsory which carries 25 marks. Answer all questions in Part A. Part B consists of 5 Units. Answer any one full question from each unit.
Part A
What is the function of a economiser?
Answer
The primary function of an economiser is to recover heat from the flue gases leaving the boiler and use it to preheat the incoming feedwater. This improves the overall thermal efficiency of the power plant and reduces fuel consumption.
Calculate the power output of a 92U 235 reactor if it takes 30 days to use up 2 kg of fuel? Given that energy released per fission is 200 MeV and Avogadro’s number = 6.023 × 10^26 per kilomole.
Answer
The number of atoms in 2 kg of U-235 is calculated as:
Total energy released in 30 days (30 × 24 × 3600 seconds) is:
Power output is:
Draw the sketch of ring mains and explain how it works.
Answer
Sign in to view the complete answer paper.
How are AC distribution calculations different from DC distribution calculations?
Answer
Sign in to view the complete answer paper.
Compare Air Insulated Substation with Gas Insulated Substation.
Answer
Sign in to view the complete answer paper.
Based on the constructional features, how are the substations classified.
Answer
Sign in to view the complete answer paper.
What is the principal cause of voltage variation? What happens if the load on the system increases?
Answer
Sign in to view the complete answer paper.
Where is the voltage control equipments placed?
Answer
Sign in to view the complete answer paper.
Name the commonly used methods for determining annual depreciation charges.
Answer
Sign in to view the complete answer paper.
Mention the advantages and disadvantages of Flat rate tariff.
Answer
Sign in to view the complete answer paper.
Part B
Give a neat schematic of arrangements of the various parts of a nuclear reactor with heat exchange, and explain.
Answer
Sign in to view the complete answer paper.
Load factor for the station is 80%. The generator efficiency may be taken as 97% and the thermal efficiency of the turbines as 28%, the boiler efficiency as 77% and the overall thermal efficiency of the whole station as 20.5%. (i) Choose the main equipment for the station. Find the size of each generator, turbine and boiler used. Give the main specification.
Answer
Sign in to view the complete answer paper.
Discuss steam station controls with reference to boiler control, turbine control and electrical control.
Answer
Sign in to view the complete answer paper.
Draw the block diagram of gas power stations.
Answer
Sign in to view the complete answer paper.
With the help of neat sketches, explain about different types of distribution systems.
Answer
Sign in to view the complete answer paper.
A single phase distributor 2 km long supplies a load of 120 A at 0.8 power factor lagging at its far end and a load of 80 A at 0.9 power factor lagging at its midpoint. Both power factors are referred to the voltage at the far end. The resistance and reactance per km (go and return) are 0.05 ohms and 0.1 ohms respectively. If the voltage at the far end is maintained at 230 V, calculate (i) voltage at the sending end (ii) Phase angle between the voltages at the two ends.
Answer
Sign in to view the complete answer paper.
Explain about a method of solving single phase AC distribution system in which the power factor of loads are referred to respective load voltages.
Answer
Sign in to view the complete answer paper.
A 3-phase, 4 wire system with 400 V line voltage supplies the following loads (i) A 400 V, 3-phase, 75 HP motor works at 0.8 p.f lagging with an efficiency of 88%. (ii) A 15W unity power factor load connected between phase A and neutral. (iii) A 12.5 kW, 0.866 leading p.f load connected between phase B and neutral. Calculate (1) the neutral current (2) the three line currents (3) total power delivered by the supply.
Answer
Sign in to view the complete answer paper.
List out various bus-bar schemes and explain.
Answer
Sign in to view the complete answer paper.
In a 3-phase, 4-wire distribution system with 240 volts between lines and neutral there is a balanced motor load of 250 kW at 0.8 power factor. Lamp loads connected between respective lines and neutral absorb 25, 75 and 100 kW. Calculate the current in each line and in the neutral wire of the feeder cable.
Answer
Sign in to view the complete answer paper.
Give the layout of a substation showing the location of PT’s and CT’s.
Answer
Sign in to view the complete answer paper.
Draw the layout diagram of gas insulated substations.
Answer
Sign in to view the complete answer paper.
What are the disadvantages of low power factor?
Answer
Sign in to view the complete answer paper.
A 3-phase overhead line has resistance and reactance per phase of 5Ω and 20 Ω respectively. The load at the receiving end is 25 MW at 33 kV and a power factor of 0.8 lagging. Find the capacity of the synchronous condenser required for this load condition if it is connected at the receiving end and the line voltages at both ends are maintained at 33kV.
Answer
Sign in to view the complete answer paper.
Mention the importance of voltage control.
Answer
Sign in to view the complete answer paper.
An Industrial load takes 80,000 units in a year, the average power factor being 0.707 lagging. The recorded maximum demand is 500 kVA. The tariff is Rs. 120 per kVA of maximum demand plus 2.5 paise per kWh. Calculate the annual cost of supply and find out the annual saving in cost by installing phase advancing plant costing Rs. 50 per kVAR which raises the p.f from 0.707 to 0.9 lagging. Allow 10% per year on the cost of phase advancing plant to cover all additional costs.
Answer
Sign in to view the complete answer paper.
How would you find the economic loading of base load and peak load stations for a given load duration curve?
Answer
Sign in to view the complete answer paper.
A generating station has a maximum demand of 75 MW and a yearly load factor of 40%. Generating costs including station costs are Rs. 80 per annum per kW demand plus 1 paise per kWh transmitted. The annual capital charge for transmission system is 20 lakhs and for distribution system Rs. 15 lakhs, the respective diversity factor being 1.2 and 1.5. The efficiency of transmission system is 90% and the distribution system is 85%. Find the yearly cost per kW demand and kWh supplied at substation and at consumer premises.
Answer
Sign in to view the complete answer paper.
What are the various types of tariff’s? Name them and explain briefly about each of them.
Answer
Sign in to view the complete answer paper.
A generating station has a connected load of 40 MW and maximum demand of 20 Mw. The units generated in an year are 60 × 10^6 kWh. Calculate the (i) Demand factor and (ii) Load factor.
Answer
Sign in to view the complete answer paper.